BUILDING ON EXCELLENCE AT 1433 CAPITAL CAMPAIGN
Our cherished KU Theta home underwent a major renovation over the summers of 2024 and 2026. For the first time in 60 years, we asked for alumnae support, and thanks to more than $2.6 million in donations, we were able to complete the long overdue project. The 2nd and 3rd floors of the house were completely redesigned, including brand new bathrooms, sleep / study rooms, fire and electrical system repair and a new, more efficient HVAC system. We made critical repairs to bring our chapter house back to the gold standard that is KU Theta, finishing on time and on budget.






CRITICAL REPAIRS &
RENOVATIONS COMPLETED
Phase 1
Completed: Summer 2024
Cost: $2.25 million
-
2nd and 3rd floor bathrooms
-
1st floor ADA compliant powder room
-
Hot water recirculation pump and loop
-
New chiller and water heater
-
West side drainage system repaird
-
Replaced three exterior doors
Phase 2
Completed: Summer 2026
Cost $3 million
-
New 2nd floor sleep / study rooms, including new beds, wardrobes, vanities, flooring and work surfaces
-
Corridor renovations, including mechanical, electrical, and fire / sprinkler system updates
-
New 2nd floor study lounge
-
New concealed heating and cooling system, replacing existing fan coil and radiator units
-
Stairways brough to code with modifications to handrails and guardrails
-
Fresh paint, a new ceiling and new light fixtures in the dining room.
-
New carpet on all stairways and upstairs hallways
-
New recessed LED lighting throughout the upstairs